You can configure as many resources as your memory resources allow. The maximum resource is 100 channels, but this can be flexible depending on available memory, and if the number of resources you need to operate is more than a few dozen channels, you may want to consider investing in multiple dedicated DRX nodes.

...

Investigate preliminary server I/O

...

load

Use the following procedure to measure the I/O load of the production server.

...